We have a big team where people work in separate tecnologies. Thus the necessity to share the team below the same JIRA project but let them (the sub-teams) to prepare their sprint separately but start all three sprints at the same day.
Hi @Jay,
It is possible if you enable Parallel Sprints
https://confluence.atlassian.com/jirasoftwareserver/using-parallel-sprints-938845513.html
You will be able to set and start multiple sprints in the same project.
Hope this helps
Have a look at the parallel sprints feature for this.
Thank you Danny! I will request the JIRA admin to find this topic there and make it available to the project of my team.