Hi @Glynnis Kearney,
Portfolio needs some kind of estimation or scheduling mechanism in order to calculate the schedule and demand.
If you have some (or all) items in your plan unestimated, you can use one of the following methods to work around that:
For more details, check out this article in Atlassian documentation.