It seems that if I have a developer assigned to two different teams and indicate the developer's availability as 40 hrs/week on each team, the scheduling algorithm does nothing to assure that developer isn't booked for 80 hrs/week. While the ability to indicate a specific number of hours per week to a team, that only seems useful when the sequence/timing of each project is already known. I'm, however, expecting/needing P4J to honor a specified capacity per resource — taking that into account when building the plan — so that I can truly benefit from the tool's ability to offer a draft plan.
Thanks!
cc: @Martin Suntinger