Hi there,
We're using Jira Cloud.
We've created a new date field (finish_date)
We'd like to populate this field automatically by adding the time estimate of a ticket to the date in the start_date field.
As far as i'm aware The fields in use have the following types:
finish_date = date type
start_date = date type
estimate = interval type
I understand that interval types can be be used to change the value of a date.
At the moment we've tried using the Power Scripts for Jira Addon but havent had any success.
date finish_date = customfield_10200 + originalEstimate; //customfield_10200 is start_date field, originalEstimate gets the value of ticket estimate
customfield_11605 = finish_date; // customfield_11605 is finish_date field.
Results in:
[SIL Error on line: 1, column: 40] java.lang.String cannot be cast to java.sql.Timestamp
Are there any other ways / addons that can be used to populate the finish_date field with the value of start_date + estimate?
Many thanks,
Dan