Hello,
A team has requested a task management project in which tracking hours per client is important. They would like to have one issue for each client. Each client can request up to eight hours of services, and these services fall into five categories, so they'd like to have five corresponding sub-tasks.
They'd like to supply an estimate of eight hours on the client's parent issue, and log their hours worked on the subtasks. Ideally, then, the work logged on the subtasks would be subtracted from the estimate on the parent issue. Is this possible?
I can't find a way to do it. The work logged on the subtasks can only be subtracted from any estimates on the subtasks themselves, not from the parent issue.
The closest approach I've found is to not supply any estimate to the parent issue, and then supply a total estimate of eight hours across all the subtasks. That way the total estimate that flows up to the parent is eight hours, and all the work on the subtasks flows up to the parent against those estimates. This is sort of ok, but unwieldy if the subtask estimates need to be changed as time goes on.
Is there any way to achieve this? Any help would be appreciated.
Thanks,
Dave