Hi all,
i am trying to make a customisation at the Burndown chart. I have set all my boards with four columns. "To-Do", "Doing", "Review" and "Done". The Burndown chart considers as "Done" and drops the line in the graph when something moves to the "Done" Column/Status but in most cases the dev team has finished their work when issue moves to "Review" column.
My problem is that in "Review" column is being created a bottleneck and this is not dev's team fault. So to have proper metrics for the progress of the dev team i need when a issue moves to "Review" column the burndown chart to lower and consider this issue as Done at least from dev team side.
Is that possible?