Hello!
We started using a tempo plugin.
And we have the following situation.
Sometimes developers have downtime in the project, for example if the customer didn't provide the api in the right time.
Our project managers want to create specific issues for these downtime in the project. But when developers have downtime, they work on the other tasks, for example they can estimate the other projects or they read technical books. In this situation they will log they work on two issues:
- downtime in the main project;
- work on the internal issues like estimation.
But this case is incorrect because developers need to log they work two times and the statistics will be incorrect.
But we need to see that developers work on the other issues because they have downtime in their main project.
How can we take into account the downtime work in the main project and in the same time the work on the other types of tasks?