There is a huge Product Backlog. I know it exists. But when I ask for it, the client, refuses to send it to me. (I'm the Scrum Master). We get a small cut of it every 2 weeks or so carved up into Sprints already.
Consequently, we have some devs that run out of work and my team of devs are not happy as their ability to decide what is in the sprint is taken away.
I've tried to reason with the client, but I think this is a control issue. They also seem to want to plan everything on their side first and are getting stuck and so the Sprint Backlogs are delayed and sometimes change. They don't see any value in consulting the dev team at the moment and I want to change this around!