Hi all!
How will the current time estimates be affected if whe change the numbers below to eight working hours a day and five days a week? Will they be recalculated in a correct way? Eg a time estimate that is 24h today will be 3 days?
/Anders
Hi Anders
All existing time estimates will be readjusted. For example, if logged work is originally set as 1d (24h), when you change the working hours to 8 hours a day and 5 days a week, the logged work will be changed to 3d.