Issues under a Business project in JIRA are not showing logged time in Tempo. Is it possible that Business type projects are not connected to Tempo?
Hi Ercella.
Business projects work with Tempo. Are you on cloud or server?
The fact that you are not seeing logged hours in your business projects could be linked to your project permissions. Maybe your business projects are using a different project permission scheme, where users don't have the correct time tracking permissions.
Regards,Sandra
Hi,
I believe I am experiencing this issue also. I have the same permission scheme in all my projects but cannot view, as a tempo admin/manager etc, any work for this project - the only one that is Business rather than Software?
Thanks,
Jimmy
Same problem here... any update / suggestion?
Emilio