I cannot drag parent issue to make the status close
I am new here in Jira. I just created an issue with subtasks under a sprint.
Our team managed to closed all subtasks but not the parent issue.
is this a workflow related issue?
thanks in advance
What is the current state of the parent ticket? It may need to be put "In progress" first.
Another way of trying to do this is, open the parent ticket. At the top there should be some buttons which relate to progressing it through the workflow, such as Start progress or Resolved which may help. If it is already in progress, there is usually a Workflow button which has the available options - what do you see there?
Check if you have a transition from current status of an issue to the closed status. You might need to transition issue to another status before closed.
You also need to check if there are any specific condition on the workflow transition. You can do this by going into workflow edit mode.
Is it safe to edit the current workflow while we have ongoing sprint?
if not, is it safe to change the workflow scheme in the middle of the sprint?
thanks in advance!
Thank you the quick response. i already tried to edit the said parent ticket but there is no option to edit the status.
my workflow looks like this:
New - In progress - Code Review - QA - Closed
and for your information this parent task came from my previous sprint carried over to my active sprint.
Hi Jeffrey
You didn't say what state the parent is in currently.
I asked that you open (not Edit) the parent, so the top looks vaguely like this
In my example, the ticket is In Review and there are buttons for Resolved and Failed Review. You won't have those options, but you may have some to help you progress it. Possibly attach a similar screenshot of your parent ticket so we can see where it is
I attached a screenshot below. i cannot locate the open from this view.