Jira, Cloud, Scrum.
We have setup up two different projects from a copy of a base project. They both have custom swim lanes. (To Do, In Progress, Reopened, In Dev, Dev Done, In Test, QA Verified) The majority of the uses see this fine. One (Admin) users continues to see different swim lanes. (To Do, In Progress, Done). It is only one user and we cannot find a configuration that is user specific.
We have found that in the URL there is a field called rapidView. For the users with the correct swim lanes the value is set to 8 (rapidView=8) For the problem user it shows as 4.(rapidView=4) If we manually change the 4 to an 8 the view is correct.
Example of problem URL. Company path removed. https://....../secure/RapidBoard.jspa?rapidView=4&projectKey=TS
Any help appreciated.