Show subtask description within task overview.
Dear Peng Zhang,
You should be able to do so under System > General Configuration > Advanced Settings.
Look for;
jira.table.cols.subtasks
Hi
Could you please explain this a bit more. I (and I'm sure others) don't actually know what you're asking, which means you're not going to easily get an answer.
Thanks
Warren
Normally in each issue, we can see the list of all sub-tasks that under it, what we could see from the task is the summary and reporter. However I would like to see the "description" and "due date" of the sub-tasks. Is it possbile to do so?
Thanks! it worked fine as it should be!
Glad I could be of service :-)
It looks like you're new here. Sign in or register to get started.