the team is not mature in agile, and i'm not able to convince them of the benefit of creating tasks! they create generic once like each user story has three tasks, one as BE, and one as UI and one as integration. this does not really give the team any transparancy as what is being worked. I am encouraging them to create tasks every day for what they plan on deliverying in a daily basis but they think this is micromanagment! I beleive a task should be self-explanatory and reflect on a job that shouldnt take more than one day of work!
any help or resources I could share with the team? cuze it's hard to manage the progress of our sprint if i cant measure it