Hello,
I'm looking to create a custom scripted field called 'Initiative End Date'. It would show on the Epic level the 'End Date' field value of the parent Initiative, which is accessible through the 'Parent Link' field that comes with Jira Portfolio.
My end goal here is JQL queries that show me when the Epic end date is later than the Initiative end date so we can adjust accordingly, and the only way I can think to do this is use Scriptrunner to pull this in as a field on the same (Epic) level, and then do a datecompare. If there are other ways, I'm open.
There are similar requests out there to pull in fields through Epic Link or subtask, but no idea where to start or the code regarding Parent Link.
Any help you can provide is much appreciated. Thank you!
-Anthony