I have Time Tracking enabled.
Before sprint start, I have estimated all sub-tasks and only sub-tasks original and remaining estimates.
Upon sprint start, the burndown chart shows a starting Original Time Estimate of 168h. (I am able to switch chart between Original Time Estimate, Remaining Time Estimate and Story Points)
Halfway during the sprint, a team member added 2 sub-tasks to an existing Story, and then edited the Original and Remaining estimate of the sub-task (like before the sprint start).
I expect the Original Time Estimate to increase due to the scope change, but there is no change in the timings on the chart.
May I know what is the intended behavior for scope changes during mid-sprint? If:
- issues are added/removed,
- sub-tasks are added/removed,
- issues or sub-tasks are moved to become sub-tasks or issues respectively within the same sprint?