Hi,
I'm a beginner to JIRA. I stared my first sprint with some stories, and the estimated time was right. After I realised I made a mistake, I deleted one of my story which was estimated to 1 week.
But deleting this story did not decrease the sprint estimation of 1 week, and I now have a week more than the addition of all my remaining stories in the sprint.