I have a task in Jira portfolio such as "acquire approval". The task itself does not take much work but then it depends on potentially 1 week of waiting. I would like to capture this as a task someone has in their lane so we can track the weekly progress and see it still waiting. But in portfolio this shows up as using a resource. However, the team member can work on other tasks while the approval process is happening via some other team. Is there a way to model this?
So if I have 10 approval requests submitted, I would like to be able to have them all start at the same time which would use a resource for a day. Then the resource would be available to do other work. Finally, portfolio should show the estimated completion of those requests 1 week from the start date.