By mistake I updated story point of a closed story in a closed sprint and reverted it back to original value. Now velocity chart is not considering that story point and chart is skewed up. It is considering story point as zero in the velocity chart.
Any workaround to get the original value show up in velocity chart?
To avoid this situation, my suggestions are:
1. Do not allow to edit story point after the sprint is closed.
OR
2. Consider original value for Velocity chart regardless of story point increased/decreased.
OR
3. Controlled Edit that only admin can modify the story point after sprint is closed (not recommended).