Hi all,
Legenda:
Have parent issue with type = Story
Have sub-task wiht type = TestTask
Lifecycle: when Story moved to TESTING tester should start testing as soon as posible (move TestTask from ToDo to In Progress)
What need to calculate:
the number of issues in sprint where the time of starting the testing the story is more than 1d
As i understand the request should be somethong like this:
project = 'TEST' and type = TestTask and ([time of transition of parent issue to TESTING] - [time of transition of current issue to IN PROGRESS] > 1d)
Does anyone have idea how to get the values for:
[time of transition of parent issue to TESTING]
[time of transition of current issue to IN PROGRESS]