Hi. I'm setting up my first Portfolio and have the Epics and Issues (Stories) displayed fine. Inside one Epic I have 2 issues that must be completed before the remaining stories (over 10) can be started. I have therefore created dependencies where the two issues "block" the remaining 10+. The problem I see is that when I recalculate the schedule the 2 issues are placed into a sprint after the 10+. i.e. In the wrong order.
Is this expected behaviour? How can I ensure that the 2 issues that must come first are displayed and scheduled before the remaining 10?