Hi All,
For the same version, my Version Report has a predicted release date of 6/22/17, whereas, the release burndown indicates three more sprints are needed which would put us at around an 8/1/17 release date. Why is there such a discrepency? I thought the Version report also calculates based off the team's velocity and the remaining estimated items. Any help would be appreciated, thanks!