Hi Guys
I read in the Atlassian Community about executing a test case (test) multiple times. Therefore you need to create multiple Test Executions.
So far so good.
So I run a Test Execution for a Test Case. It faild for a specific Build-Number (or Version). In the next build (Version), the bug was fixed, so a created another Test Execution (a clone) for the new Build-Number. This Test Run was successful.
Now, the overall Execution Status in my Test Plan shows 1 Fail. This is actually correct, but I am only interessted in the last, successful Test Execution for the Test Case.
Is it possible to show only the last Test Execution for a given Test Case?
Kind regards
Aleks
P.S. We are using Jira Xray 2.1.3