So, picture with me there is one user story. and we have let's say three developers, each one of them has created one sub-task for that user story to complete. Let's say that each one of them has estimated that it will take one day to complete their his/her task.
in the above scenario, and according to Jira setting, once you do the above, it will tell you that the user story in question requires 3 days to complete!!! where in fact it should take only one day since we have 3 developers and each will work on their own and would consume one day to finish!! that is what i dont get.
same issue above appears when i make a sprint, we drag all the user stories along with their sub-tasks. we have a four week sprint and we have allocated real estimation for the four weeks, but all the sudden because JIRA adds up all time it suggests that the remaining work to be done is something like hundred of weeks!!!?
Many thanks