Hello,
I have an issue with the remaining estimate tab. Basically I can not change the remaining estimate from the plan view for user stories with subtasks.
When i click edit the remaining tab doesn't appear. Only when creating issues this tab is available.
Although when looking at a story and its subtask, next to the status you see the remaining estimate but that cannot be changed. Just the original estimation can be changed.
How can I change remaining estimates?
Thank you,
Silviu.