Hi people,
i have a service desk in which i have issues that have due dates in a few days (even weeks). These issues will remain untouched by a technician until a few days before that due date. I currently have SLAs on these issue, but the SLAs starts as soon as the issue is created, so the SLAs are wrong.
How do you guys manage these situation? I can think of a few way to fix this, but i'm not sure which one is the best!
- Adding a status that "pause" my SLA, until the technician starts working on it, but it opens a door to the technician to put issues in a loop status that would permit him to bypass SLA.
- Modify my JQL in SLA so it doesn't catch task with due dates (since the date is already the SLA)
What you guys think of that situation?
Thanks,