I have created few test issues in a new project. Now I want to delete them and make the issue numbering to start from the begining, rather than the last issue's number + 1.
Is this possible with either database manipulation or just from frontend?
We use Oracle 11.2.
Write down the project's settings (schemes etc), then delete the project (which will kill all the issues as well) and then create it again with the same short code.
For database manipulation, delete all the issues in the UI first, stop Jira, get a backup (although this is unlikely to cause a fault), open up the "project" table and change the pcounter to 1 (That's from memory - it might be 0, you can check this by creating a new empty project and reading the pcounter for that from the database to confirm it)
Thanks!
It's just a simple SQL then!!
update project set pcounter = 0 where pkey = 'PROJ'; commit;
DB manipulation seems to be the easiest option, however it's better to test it on a test environment first.
Definitely test it :-) I prefer the db change as well myself, because I'm lazy and don't want to have to put all the schemes back.
Just make sure you have Jira offline when you do it. Project counter keys are one of the things it almost always caches, so if it's running when you make the change, you could see it wiped out by the cache.
You may do it without restarting JIRA instance by using script runner plugin and this piece of groovy:
import com.atlassian.jira.ComponentManager
ComponentManager cm = ComponentManager.getInstance()
def pm = cm.getProjectManager()
pm.refresh()
Hello, This thread is a bit old but this KB is new and may help someone. https://confluence.atlassian.com/display/JIRAKB/How+to+reset+the+project+counter+after+moving+issues
When there are moved issues another table needs to be changed, the moved_issue_key.
Thanks for this
Hi, I have tried to perform this proceedure again on another JIRA instance but I get that the object name "project" is invalid. Any idea?
Check the syntax guide for your database.
For those who are not SQL experts (like me) here is the proceedure I followed:
O.S.: Windows Server 2012 R2
SQL Server version: 11.0.60.20 (2012)
JIRA schema: "jiraschema"
IMPORTANT: As Nic told before, you must stop JIRA and perform a backup before peforming these changes
20160914_JIRA_ChangeKeyNumber.PNG
(i) It´s was translated by me, so some names can be different
Hello guys, just to give more information about the procedure given by Sameera Shaakunthala [inactive] Feb 20, 2013:
Speccialy for who doesn't know so much about Linux commands and has an enviroment hosted on Linux machine:
1-First you have to stop jira service on Linux machine:
~$ sudo service jira stop
2-Confirm if the service is really inactive/stopped:
~$ service jira status
3-A line like this should be appear:
Active: inactive (dead) since...
4-Then, let's logon into mysql (here the user for mysql is 'root'):
mysql -u root -p
5-On command line should appear 'mysql>', where you'll type the following command, just attention that 'jiraservicedesk' is the name for the Jira Service Desk Database:
USE jiraservicedesk
6-Finishing you'll type the procedure given by Sameera:
update projectset pcounter = 0where pkey = 'PROJ';
7-This message will appear on screen:
Query OK, 1 row affected (0.01 sec)Rows matched: 1 Changed: 1 Warnings: 0
8-This last command is just to start jira service again:
~$ sudo service jira start
For Linux commands, these websites helped me so much:
Thanks Sameera and all!
Hi all,
actually you can reset the project key when using scriptrunner. Here is the snippet, but be careful when using it
https://bitbucket.org/janszczepanski/workspace/snippets/oBkRLy
Um, no, that could easily fail, as you've not taken account of the caches. I don't think SR can even clear the cache you would need to hit.
Your script could only work safely if you stopped Jira, restarted it, run the script before anyone starts using Jira projects, then stop and restart it again.
@Nic Brough -Adaptavist- Is that mean we can accomplish this by following the 'SR' if we stopped Jira and perform the SR actions?
@Jan Szczepanski
No. If you stop Jira, you can't run scriptrunner scripts.
It looks like you're new here. Sign in or register to get started.