I'm evaluating Tempo to see if it can replace our current system for traditional task and project planning (not Agile). To manage the IT portfolio right now, we use MS Project and a series of spreadsheets that require manual intervention to keep the two synchronised.
JIRA and Tempo have ticked a lot of boxes so far, but as far as planning goes, I've found lacking in some key areas. For example:
- speed
- predecessor/successor relationships
- cascading changes (e.g. change a task duration, all subsequent tasks move accordingly)
I've had some difficulty integrating / importing between Project and JIRA, but those are separate issues. I'd love to know: is there an add-on or plugin for JIRA that allows for efficient project planning?
I'm not talking multi-year, thousands-of-tasks projects - more on the 3-6 months, 1-200 tasks scale.