I've set up a plan in JIRA Portfolio with a release that began in Aug 18th (about 2 weeks ago) and will complete at a future date. If I mark one of the epics in that release as complete (which it is), Portfolio removes it from the plan and schedules something else to begin on the 18th - 2 weeks in the past!
Am I missing something here?