I am currently using portfolio in jira. In portfolio we can get workload of a team member in a given plan.
But if a person is in two teams. Each team is in different plans. Workload of person is not summable that is they are independent of each other. So person is allocated twice his capacity to work. So I want to change from portfolio to others like tempo folio.
I want to know whether tempo folio maintains complete list of people while calculating workload or it calculate as per teams as in portfolio.?
Thank you in advance