If an issue has an original estimate of 40 hours and remaining estimate of 16 hours, when that issue is moved to the next sprint at sprint close, will there be a new original estimate of 16 hours?
No. These values won't change when an issue is moved to the next sprint at sprint close.
I seem to recall other scrum management tools like Version One doing something like that when "splitting" an issue, but JIRA Agile doesn't do that.
Yes, it's a spectacular pain when software does that, you can't get any useful judgement on how well your estimates are working out.
Agreed. However, then it dooms the next sprint to have bad estimates at the outset unless they are adjusted. Thanks!
Thanks to all for the comments! My question is answered.
No problem. I feel cheap asking that, but could you "accept" the answer? I'm starting to build up my stats
Well, not really, because you've still got the original estimate. If you decide it's completely wrong, that's fine, you can change the remaining estimate and still retain the information that your original estimate was not as good as it cold have been.
absolutely!