This question is in reference to Atlassian Documentation: Using the release page to check the progress of a version
I have found this comment on GHS-8152 from 2013-11-26 saying:
We have decided to remove sub-tasks all together from the Version Report. This will be present in JIRA Agile 6.3.6.
If there is a legitimate use case for displaying sub-tasks on the Version Report, we will address it later. But by default we believe that most users do not benefit from sub-tasks being included.
Thanks for your patience.
Regards,
JIRA Agile Team
But open opening a Version Report (aka Release Report?) in JIRA version 6.4.12 (per instructions here) and clicking, for example, 42 Issues to do, many of the issues then listed below are sub-tasks. How I can remove those sub-tasks from the list?