Hi,
I just found out that issues imported in portfolio have estimate as remaining estimate for parent issues.
In the board plan mode as well the estimate field just shows original estimate for parent issues(excludes for sub-tasks).But using script runner i managed to get thgis estimate field display the total original estimate for parent issues and sub-tasks. However remaining estimate field shows correctly for parent issues as it shows as sum of the value for parent and sub-tasks. Now when we import issues in portfolio, we still see that estimate column shows only remaining estimate for parent issues and excludes for its sub-tasks.
Could you pleas help me implement something to resolve this.
BR,
Ashley