We just finished a sprint in which, according to the Release Burndown chart, the point stats look like this:
736 at start of sprint
42 added to version
6 completed
772 remaining
However, during the sprint we 'Resolved' a large story sized at 21 points because we're not going to do it (I can confirm this on my Sprint Report). So from a release standpoint, those 21 points need to come off of the 772 remaining points as well but as you can see, they haven't.
Why is this?
Thanks