We had following questions and required you to help us solve following use case:
A) We have multiple projects created within JIRA each representing a different development sub teams working on same application development.
We would like to have ONE COMMON TEST PROJECT for all sub teams. However we saw that “the PLAN TEST CYCLES page shows all the test cycles” and this will be a problem if we go to create test cycles for all sub projects. The page would look cluttered and unmanageable.
To counter this, we thought of maintaining tests repository in one common TEST project but create/maintain TEST CYCLES/Metrics/Dashboards/Execution Data in respective different jira (sub) projects.
But in that case we were not able to Create Test Cycle in Project_X and add test cases from common TEST project. Tests from other projects cannot be added to test cycles in my project!
How do we allow to add tests from other projects and create test cycles with different sub projects?
Aletrnatively, can we have filters on TEST CYCLE - MANAGE page, to just show my test cycles of my project.
Please help.
Other Features - Nice to have:
1.
In the “Create Test” process, we saw that the STEPS for the TEST CASE are added in the SECOND attempt.
Person has to first load create test case form, fill details(other than test steps) and click CREATE and then again on the loaded Test Form fill all the “steps” for the test case.
Can we not have a single form which also allows us to add steps in one go while the other fields for test case are filled. Is this configurable at our end?
C) Also can we not have the normal “Create Another” checkbox on create test page which we otherwise have for other jira ticket types.
This will allow us to retain some same values/fields and create new test cases.
Please suggest.
Thanks and Regards
Prakash Borkar