Hello,
I cannot seem to get Sub-tasks to appear on my Live Plans. I confirm that my Hierarchy levels are set to default: image2016-5-25 13:22:0.png
I can create a new sub-task from the live board under a story, and it successfully creates the issue, but on refresh the sub-task does not appear on the board.
Update:
I have found out why the Sub-Tasks are not appearing. We have made a field configuration change to hide 'Fix Version' on our Sub-Tasks because we want to control that at the Story and above level. Having this field hidden is causing the Sub-Tasks to not appear on the Live Plan. I can confirm that showing that field causes the items to start appearing on the Live Plans. Can someone explain this behavior?