Hi,
Im looking to see if JIRA is something my company could use.
Our current in house system uses a single tasks with a workflow, during which there are 3/4 dates that need to be met at various stages in the workflow.
ie
Task1 (task type - New Customer Investigation) - Due date 15/1/15
- Step1 - Due 1/1/15
- Step2 - Due 5/1/15
- Step3 - Due 10/1/15
Can this be done in JIRA by using workflow or would subtasks work better?
If subtasks, then can template tasks be setup so that when you create Task1 with a due date, it knows its a new customer investigation and will create the necessary subtasks and automatically caluclate the dates based on rules?
ie
Task1 (task type - New Customer Investigation) - Due date 15/1/15
- Step1 (Due date = Parent task due date - 15 days)
- Step2 (Due date = Parent task due date - 10 days)
- Step3 (Due date = Parent task due date - 5 days)
The reason for this is there are hundreds of tasks each week and to manually have to put in all the sub tasks with the correct due dates would be impossible.
Many thanks,
James