I love how the children estimates roll up into the parent, but I see one problem with this. Let me describe:
- The parent item is created. No original estimate is specified.
- Two children tasks are created with estimates of 3h and 5h. The parent's estimate is now 3 + 5 = 8h.
- The parent is now officially considered "planned." the team expects 8h of work is all that's needed to accomplish the work.
- Work begins on this parent item.
- Two days later, someone realizes another tasks is necessary, creates this task, and estimates it at 5h. Parent estimate is now 13h.
ohhh noooesss!!! the parent's original estimate should not have been increased to 13h. It should remain at 8h since that's the final estimate before work began. so my question is this ...
how do you "lock" the original estimate at a certain point in the workflow?