In Confluence 4.0 is there a way to schedule the confluence backup to run on a specific day of the week, say every Saturday at 2am? I can't seem to find a cron expression to let me do that.
Hi Ray,
This expression should work for every Saturday at 2am:
0 0 2 * * 6 ?
Hope that helps,
Andrew.
Thanks for the expression but when I do that I get the following validation error:
"
Thanks Andrew! That works, I only had to change the 6 to 7 because if I used 6 it was saying that was a Friday and not a Saturday. I'm assuming that's because the cron expression has Sunday as the 1st day of the week.
Same error for me