Could you please explain how progress is calculated? Below you have a project with total estimated = 16. The project has two tasks, an estimated of 8 hours each task, the first task is finished with 8 hours registered. So the progress is 50% (8 hours finished of 16 hours. 1 day finished of two days. 1 task finished of two tasks of the same duration and estimation). According to JIRA time tracking report the progress is also 50%; BUT the progress in the gantt-chart - as you can see below - is 66%. Could you please explain why? Thanks!
