Screen Shot 2014-11-18 at 19.47.46.png
As you can see from the image above, I have an epic called "Setting up office environment" , the duration of this task, as you can see in the yellow box, is "3 working days".
The epic contains 3 issues:
- SW-33: Estimated 2 days 2h 36 minutes and done by me exactly on time.
- SW-4: Again, Estimated 2 days 2h 36 minutes and done by my college exactly on time.
- SW-14: Estimate as 2 hours and done by me exactly on time.
The point is SW-33 and SW-4 done simultaneity by me and my college together in the same days.
Images are as below, from left: SW-33, SW-4, SW-14
Screen Shot 2014-11-18 at 19.53.53.png
_______________________________________________________________
Screen Shot 2014-11-18 at 19.54.09.png
________________________________________________________________
Screen Shot 2014-11-18 at 19.54.26.png
The problem is that the Gantt-chart plugin marked the epic as "Over-capacity: planned 166% allocated work, current need: 0%", which is wrong . Actually I think its calculated as followings:
((∑Original estimates)/(Duration))*100
In this case
((0.33+2.33+2.33)/(3))*100=166%
Which is wrong, because the task is not over capacity and the epic distributed between 2 people and it can be done in 3 days. Because the two 2.33s in the above calculation were done simulantely , I think it must be calculated as this (it can be rounded or calculated other ways)
((0.33+2.33)/(3))*100
What's wrong ? Is it really the problem ?