Does anyone know how the completed points field gets populated?
This feature does work well out of the box. But we changed a number of things, and now the data is not showing correctly.
1. The filter for the board encompases the issues
2. The workflow is mapped (although I deleted old statuses)
3. The points associated with done issues in the sprint are simply not being counted for some reason?
A picture of the problem - no completed work indicated when there are stories with points that are "done".

Sprint Report - shows we did burndown/complete work. Sprint report doesn't list completed issues though?

Sprint Export - Clicking the link show issues in Navigator and exporting shows "Done" issues (completed?) with points.