Hello,
I am unable to import Sprint from CSV. Could anyone suggest me the procedure. The Sprint values (Sprint 0, Sprint 1 ....)are not supporting.
If it is not possible through CSV is there any other method?
Regards,
Krupasindhu
We would like to inform you that mapping the sprint number isn't possible in JIRA when importing via CSV. However, there's a feature request which has been raised for this functionality. For your reference, please see https://jira.atlassian.com/browse/GHS-5942.
We suggest to complete the import first and then perform a bulk edit to update the Sprint name (the field name is Sprint) for the relevant issues
Thanks I'll do that manually. We are hearing this since 2012 that in next 12 months JIRA is going to update the sprint import from csv. Do we have any update that this can be added in next release?
No, I already added the ticet number above.
@Dionisio Gomes is right, there is a way to add the Sprint ID, which is a number, to the .csv file when importing using the External System Import tool.
To get the sprint id, go to Search for Issues, Advanced Search, enter the name of the sprint in the search bar. For example,
sprint = name of your sprint
The sprint id will appear as a number in the place of the 'name of your sprint' above.
Copy the sprint id number and insert the id number into your .csv file and ensure that the column for the sprint field is a number field with no decimal points.
Your issues will import with the correct sprint.