We have a client where we encountered the following situation:
- TEMPO installed, everything is ok, they use the approve timesheet stuff, and status is ok: 'ready' for past time intervals, 'open' for the current, 'approved' & 'rejected' if it was the case
- We installed JIRA Agile
- TEMPO timesheet status is reset to the 'ready' state for all timesheets, no matter if they were approved or not. For new timesheets, approval works correctly, but for those pre-existent just before JIRA Agile install, it does not work ('ready' status only)
We would love to fix this ASAP, does anybody have a clue what's going on there?