Dates roll-up in our Jira plan broke this morning. I’m not really sure what caused it, but now I only see rolled-up dates for one Epic.
I’ve already checked the following without success:
Plan settings (hierarchy, scheduling, timeline options)
Issue sources and filters
View settings (including “Show rolled-up dates”)
Despite that, most Epics don’t display rolled-up dates anymore. They worked fine before today.
As you can see, roll-up only works for the first Epic.
Would appreciate any help troubleshooting this.