Hi All,
Im attempting to get 5 working days from issue.getCreated() but im having alot of issues, please see code below:
import com.atlassian.jira.component.ComponentAccessor
import com.atlassian.jira.issue.CustomFieldManager
import com.atlassian.jira.event.type.EventDispatchOption
import com.atlassian.jira.issue.UpdateIssueRequest
import com.atlassian.jira.issue.MutableIssue
MutableIssue issue = ComponentAccessor.getIssueManager().getIssueObject('COM-2479')
CustomFieldManager customFieldManager = ComponentAccessor.getCustomFieldManager()
Date createdDate = issue.getCreated()
Date date = new Date();
Calendar calendar = Calendar.getInstance();
date = calendar.getTime();
//SimpleDateFormat s;
//s=new SimpleDateFormat("MM/dd/yy");
int days = 5;
int i=0;
for(date;date<createdDate;)
{
calendar.add(Calendar.DAY_OF_MONTH, 0);
if(calendar.get(Calendar.DAY_OF_WEEK)<=5)
{
i++;
}
}
//date=calendar.getTime();
//s=new SimpleDateFormat("MMM dd, yyyy");
return createdDate+i