I am trying to associate Releases (FixVersions) with the Time Boxes created in my Big Picture plan. I don't see "Release" as an option, as I have seen in my previous lives.
- Plan consists of a single project with Story and sub-task issue types, only.
- Project in the plan is a JSM project
- Releases with dates have been created
- Issues have FixVersions applied
- Teams within BigPicture have been created
- Issues have been assigned to Teams using the Team#Label
- No Sprint Boards or Kanban Boards are associated with the project
- Task Structure is "agile", though I've tried a few iterations of custom with no change
- Scope includes Issues and Versions
What am I missing? Is it because it's a JSM??