I encountered a weird problem with mixed up sprints.
We manage multiple projects and each project has its own sprints (sprints are named differently (<Project_Name> | Sprint <Month>.<Year>) or something similar to that. But they all are never the same.
This issue happens again for a second time --the first time it happened was last year but it was too late to fix anything because the sprint had already started.
So, we create several sprints per project beforehand (5 or 6 sprints in advance). But there will always be one of the sprints gets mixed up with another project.
Following are what correct sprint names are supposed to look like:
Project A
- Project A | Sprint 1.2025 (active sprint)
- Project A | Sprint 2.2025 (future sprint)
- Project A | Sprint 3.2025 (future sprint)
- Project A | Sprint 4.2025
- Project A | Sprint 5.2025
Project B
- Project B | Sprint 2025.1 (active sprint)
- Project B | Sprint 2025.2 (future sprint)
- Project B | Sprint 2025.3 (future sprint)
- Project B | Sprint 2025.4
- Project B | Sprint 2025.5
But this is what we get:
Project A
- Project A | Sprint 1.2025 (active sprint)
- Project A | Sprint 2.2025 (future sprint)
- Project A | Sprint 3.2025
- Project A | Sprint 4.2025
- Project A | Sprint 5.2025
Project B
- Project B | Sprint 2025.1 (active sprint)
- Project A | Sprint 2.2025 (future sprint)
- Project B | Sprint 2025.3
- Project B | Sprint 2025.4
- Project B | Sprint 2025.5
Even if we delete the problematic sprint and create a new one in the correct project, in this example above -- we delete the Project A | Sprint 2.2025 from the Project B and create a new one in the Project B, the newly created sprint is incorrectly linked to the Project A. Then it would look like:
Project A
- Project A | Sprint 1.2025 (active sprint)
- Project B | Sprint 2025.2 (future sprint)
- Project A | Sprint 3.2025 (future sprint)
- Project A | Sprint 4.2025
- Project A | Sprint 5.2025
Project B
- Project B | Sprint 2025.1 (active sprint)
- Project B | Sprint 2025.2 (future sprint)
- Project B | Sprint 2025.3 (future sprint)
- Project B | Sprint 2025.4
- Project B | Sprint 2025.5
We check the Sprint ID of the problematic sprint, and they share the same Sprint ID across 2 projects. The same happens if we rename it -- the renamed problematic sprint gets updated in another project.
Has anyone ever enountered this? Do you know how to fix this?