We are seeing inconsistencies in remaining Epic hour estimates across JIRA and JIRA Portfolio.
Example:
Epic-XYZ has remaining estimate equal to 570 hours
- In JIRA, ran a simple JIRA query of Epic link to pull child issues and sum remaining hours
- In JIRA, shown within Epic-XYZ with the use of the of the "Epic Sum Up" plugin
Epic-XYZ has remaining estimate equal to 537 hours
- In JIRA, shown within JIRA Epic-XYZ under "Time Tracking"
Epic-XYZ has remaining estimate equal to 557 hours
- In JIRA Portfolio, shown in the "Estimate (h)" column
Epic-XYX has remaining estimate equal to 730 hours
- In JIRA, shown within the Epic-XYZ Epic report
We are unsure why there is no consistency between the three locations, especially the "Time Tracking" which we assume should equal the "Epic Sum Up" or Epic report.
Thank you!