Hi
I had an internal Tempo issue called "Meetings" which was used for logging any meeting hours against. Its key was previously ABD-11.
I renamed the project's Key from ABD to ITS, and the issue got renamed ITS-11. It even shows up in the list of internal issues in the Tempo Administration screen. All looking good so far.
However it seems to have lost the internal issue 'behaviour', namely that I shouldn't have to enter a remaining estimate, when I log time against it. Also, I can't delete it from the list either.
Has anyone else had any experience of this (and ideally, know what the fix is?)
Thanks